The first Saturday that the builders worked. As the roof guys were rained off yesterday they came in today to finish the roof. The zinc flashings were added and the flat roof had its final cover of gravel and sticky black stuff.

Inside the plasterboard was completed, all ready for plastering tomorrow. Yes, the plasterer (sub-contracted by the builders) is in on a Sunday to put the plaster on the walls.

Finished roof
Finished roof
Plasterboard on the walls
Plasterboard on the walls
This door is coming out on Tuesday after the new French doors arrive
This door is coming out on Tuesday after the new French doors arrive
Plasterboard in the corners of the wall and vaulted ceiling
Plasterboard in the corners of the wall and vaulted ceiling

2013-08-17 17.21.29 2013-08-17 17.21.32 2013-08-17 17.21.37 2013-08-17 17.21.45

Roof flashing against the house
Roof flashing against the house

2013-08-17 17.33.13